Capital planning with decision checkpoints

Investment, governance and budget

The source outlines a conceptual USD 11 billion envelope over ten years, including USD 750 million for the three medical complexes and USD 10.25 billion for the remaining scope. These are source estimates, not an investment valuation or a guaranteed return.

Architectural concept from the project atlas
Development statusA vision in planning and development

Plan reference: 13 May 2026

Phases and decision gates

Basis and limits of the estimate

This is an early estimate with expected accuracy of approximately ±25–30% before surveys and design. Amounts in US dollars are used for planning and include the construction, equipment, design, permits, escalation, transport and contingencies shown.

The envelope excludes financing interest, debt issuance costs, initial operating losses, working capital, unresolved taxes and unknown site compensation. Operations, revenue and financing need separate models before a final investment decision.

Initial annual operating costs at completion are estimated at about USD 550–850 million, outside the USD 11 billion. They vary with wages, energy, airport and port traffic, and the treatment and subsidy model.

Comprehensive founding report · Source pages: 1، 3، 4، 5، 25، 27 ↗

Full capital budget

No.ItemUSD million
1Rights options, surveys and due diligence250
2Site preparation, coastal protection and environmental works300
3Public airport capable of qualifying for international status1,800
4Commercial port, marina and ferries1,150
5Roads, electric transport and utility corridors500
6Energy, smart grid and storage800
7Desalination, water, wastewater and reuse400
8Fibre, communications, data centres and security350
9Automated warehouses, cold chain and inventory400
10Beverage, packaging and food processing plants300
11Fruit and vegetable farms and greenhouses250
12150 smart villas and their facilities300
13Retail complex, hotel and family services225
14Shared AI and robotics platform400
15General hospital, security, emergency services and staff housing400
16Master design, permits, programme management and testing300
17Early price escalation allowance425
18Imports, transport to the site and construction escalation800
19Owner’s contingency for risks and changes900
Total infrastructure and services outside the complexes10,250
Three medical complexes750
Final total11,000
Comprehensive founding report · Source pages: 26، 27 ↗

Allocation and contingency control

USD 750 million for the complexes + USD 8,125 million for items 1–16 + USD 2,125 million for escalation, transport and contingency = USD 11,000 million. Any increase in scope or capacity requires an approved reallocation or separate financing.

  • Maintain 500,000 m² as the land area of each complex; treating it as built floor area is incompatible with the complexes’ budget.
  • Select suitable natural land for the airport and a deep, sheltered coast, and phase development with demand over two or more stages.
  • Protect the owner’s contingency from aesthetic additions and unfunded capacity until site, aviation, port, soil and environmental risks are resolved.
  • Update costs after surveys and at 10%, 30% and 60% design maturity, using an independent estimate.
  • Link contracts to performance, energy, maintenance, localisation and data; do not finalise purchases before due diligence is passed.
Comprehensive founding report · Source pages: 27، 29 ↗

What could change the cost

DriverSensitivityEffect
Marine reclamation for the runwayCriticalCould add billions and rule out the site
Breakwater and dredgingCriticalCapital, environmental and ongoing maintenance costs
Land rightsHighBase allowance is only USD 250 million
Soil and liquefactionHighGround improvement and foundations
Shipping and importsHighMedical, port and energy equipment
Currency and inflationHighMulti-currency contracts and hedging
Early capacity expansionHighAddressed through phasing that demonstrates demand
Comprehensive founding report · Source pages: 27 ↗

Separate entities and clear responsibilities

Proposed entityRole
HoldCo PT PMAOwnership, financing, governance and shareholder agreements
AssetCo / DeveloperLand rights, shared infrastructure, development and leasing
HealthCo / MedTechCoHealthcare complexes, with the medical device business separated to avoid conflicts of interest
Airport SPVAirport development, concession and operation with an approved operator
Port SPV / BUPPublic port, concession and marine services
Utility SPVEnergy, water, wastewater and waste
DigitalCoFibre, data centres, robotics and security
Agri-FoodCoAgriculture, factories and associated warehouses
Hospitality / Real EstateVillas, hotel, retail and staff housing
Optional YayasanGrants, charitable treatment and community research within its licensed remit
Comprehensive founding report · Source pages: 5، 6، 24 ↗

Governance committees and contracting model

  • An investment and projects committee oversees scope, budget, contracts and value engineering. An audit and risk committee oversees finance, compliance, insurance, procurement integrity and conflicts of interest.
  • A medicine and ethics committee covers quality, safety, rights, research, medicines and devices. An AI and data committee covers models, privacy, security, licences and incidents.
  • An environment and community committee covers AMDAL, biodiversity, rights, access and grievances. A safety and security committee covers aviation, maritime operations, utilities and disasters.
  • Separate sector EPC contracts with a central integration manager, plus long-lead supply packages for devices, turbines, transformers, desalination, fibre and port equipment.
  • Operations and maintenance or concession contracts include performance indicators, training, knowledge transfer and spare parts within Indonesia.
  • Open-book pricing during design, followed by a guaranteed maximum price once scope and surveys mature; independent value engineering reviews at 10%, 30% and 60%.
  • Shared data, security, robotics and procurement services with clear pricing and data transfers, and separation of high-risk assets.
Comprehensive founding report · Source pages: 6، 24 ↗

Capital allocation in the source chart

GroupUSD billionPercentage shown in source
Three medical complexes0.7506.8%
Direct project facilities8.12573.9%
Escalation, transport and contingency2.12519.3%
Comprehensive founding report · Source pages: 26 ↗